← All projects

Project case study · Grid-connected renewable energy

20 MWp Utility-Scale Solar Power Station — Uganda

Uganda, East Africa

Utility-scale ground-mounted solar photovoltaic array
20 MWpInstalled solar PV
10 MWhBattery storage
40,000Ground-mounted modules
33kVGrid export

Executive summary

This case study presents the development, engineering, installation and commissioning of a 20 MWp utility-scale solar photovoltaic power station in Uganda.

RESDAC Systems Limited designed, installed and project-managed the fully integrated solar and battery-storage facility, exporting power at 33kV to the national grid.

The facility strengthens Uganda's renewable-energy portfolio while improving grid stability and peak-demand management.

01

Background and objectives

Growing electricity demand and national renewable-energy targets created the need for clean generation capacity that supports grid stability, reduces reliance on fossil-fuel peaking plants, improves electrification reliability and contributes to national climate commitments.

Project objectives

  • Develop a 20 MWp grid-connected solar plant
  • Integrate 10 MWh battery storage
  • Export at 33kV through a dedicated switchyard
  • Maintain availability above 99% and optimise performance
  • Operate securely through a centralised EMS
02

Site and security

Site

  • Location: Uganda, East Africa
  • Total area: 100 hectares
  • Predominantly flat topography
  • Utility-scale renewable-energy land use
  • Fully fenced perimeter with integrated monitoring

Security infrastructure

  • Anti-climb fencing
  • Vibration-detection cables
  • Day/night IP cameras
  • Controlled-access gates
  • On-site security personnel
  • Integrated alarm reporting to the CCR
03

System design

Solar PV array

  • 20 MWp installed capacity
  • 40,000 ground-mounted modules
  • 2 × n dual-row layout
  • 20 MW AC capacity
  • Distributed inverter topology

Why the 2 × n configuration

  • Optimised land use
  • Improved airflow and thermal performance
  • Efficient maintenance access
  • String balancing
  • Reduced shading losses

Inverter system

  • 40 × 500 kW networked inverters
  • Real-time monitoring and remote diagnostics
  • Power-factor control
  • Voltage and frequency regulation
  • Redundancy, fault isolation and maintenance flexibility

10 MWh Battery Energy Storage System

The BESS is grid-connected through an EMS-controlled interface.

  • Peak shaving
  • Ramp-rate control
  • Frequency support
  • Voltage stabilisation
  • Energy shifting
  • Improved dispatch flexibility and grid compliance
ParameterSpecification
Installed capacity20 MWp
Modules40,000
MountingGround-mounted
PV configuration2 × n dual-row
BESS10 MWh
Grid export33kV
04

Grid connection and 33kV switchyard

The on-site switchyard exports power at 33kV and provides safe synchronisation, fault isolation, revenue-grade metering and grid-code compliance.

  • Step-up transformers
  • 33kV circuit breakers
  • Protection relays and coordination
  • Metering equipment
  • SCADA integration
05

Control and monitoring infrastructure

Central Control Room

  • Energy Management System
  • SCADA servers
  • Communication infrastructure
  • Grid-interface controls
  • Security-system monitoring
  • Environmental dashboards

Energy Management System

  • Real-time plant monitoring
  • Inverter-level diagnostics
  • BESS dispatch control
  • Alarm management
  • Remote access
  • Historical analytics
  • Grid-support functionality
  • Integration of PV, battery, switchyard protection and security systems
06

Engineering and project delivery

Engineering

  • Site feasibility and geotechnical assessment
  • Electrical and civil design
  • Protection, load-flow and short-circuit studies
  • Grid-interconnection design
  • Security-systems engineering

Construction

  • Site preparation
  • Mounting structures and 40,000 panels
  • 40-inverter deployment
  • DC/AC cabling and trenching
  • Transformers and 33kV switchyard
  • 10 MWh battery integration
  • CCR and perimeter-security construction

Project management

  • End-to-end project management
  • Procurement coordination
  • Contractor supervision
  • QA/QC and HSE
  • Schedule and budget control
  • Commissioning oversight
07

Health, safety and environment

  • Full HSE management plan
  • Zero major lost-time incidents
  • Environmental-impact mitigation
  • Dust suppression
  • Controlled waste management
  • Biodiversity protection
08

Commissioning and performance

The plant achieved commercial operation following utility approval.

Testing

  • String testing and IV-curve verification
  • Inverter functional testing
  • Transformer and switchgear testing
  • Protection-relay calibration
  • Battery performance testing
  • SCADA and EMS integration
  • Grid-synchronisation approval

Expected performance

  • 20 MWp installed capacity
  • Availability above 99%
  • Industry-compliant performance ratio
  • Annual generation dependent on site irradiation
  • EMS-optimised battery dispatch

Grid impact

  • Improved voltage stability
  • Reduced intermittency
  • Peak-demand support
  • Reduced fossil-fuel dependency
09

Economic and social impact

Economic impact

  • Increased renewable capacity in Uganda
  • Reduced carbon intensity
  • Long-term electricity-price stability
  • Attraction of green investment

Social impact

  • Local employment during construction
  • Skills transfer to local technicians
  • Improved regional energy reliability
  • Support for national energy-access goals
10

Risk management and lessons learned

Risks mitigated

  • Grid instability through BESS
  • Equipment failure through distributed inverters
  • Security threats through integrated surveillance and vibration detection
  • Weather impact through robust mounting
  • Downtime through EMS-driven predictive maintenance

Lessons learned

  • Early grid coordination reduces commissioning delays
  • Integrated EMS and BESS improve dispatch value
  • Distributed inverter topology improves maintainability
  • Security integration belongs in the design stage

Sustainability impact

Engineering that moves the energy system forward.

  • 100% renewable energy generation
  • Significant annual CO₂-emissions offset
  • Support for Uganda's renewable-energy strategy
  • Alignment with global climate objectives

Explore the complete RESDAC project legacy.

Back to the timeline