← All projects

Project case study · Captive power

20 MWp Utility-Scale Solar Power Station — Captive Industrial Supply

Nigeria, West Africa

Ground-mounted solar photovoltaic array
20 MWpInstalled solar PV
40,000Ground-mounted modules
33kVDirect industrial supply
>99%Target availability

Executive summary

This case study presents the development, engineering and delivery of a 20 MWp utility-scale solar photovoltaic power station in Nigeria.

Designed, installed and project-managed by RESDAC Systems Limited, the facility supplies renewable energy directly to a multi-industry industrial area operating as a captive customer through a dedicated 33kV distribution network.

The project provides stable, cost-effective clean power while reducing dependence on diesel generation and an unstable grid.

01

Background and objectives

Nigeria's industrial sector faces grid unreliability, high diesel costs, voltage fluctuations and production downtime. A dedicated renewable facility was developed under a private-power arrangement to address those constraints.

Project objectives

  • Develop a 20 MWp captive solar plant
  • Deliver direct 33kV supply to an industrial cluster
  • Reduce diesel-generator reliance
  • Improve voltage stability and power quality
  • Ensure availability above 99%
  • Provide centralised monitoring and operational control
02

Site

  • Location: Nigeria, West Africa
  • Site area: 100 hectares
  • Land use: dedicated renewable-energy generation
  • Adjacent to a multi-industry industrial estate
  • Dedicated service road and controlled entry points
03

System architecture

Solar PV array

  • 20 MWp installed capacity
  • 40,000 ground-mounted modules
  • 2 × n dual-row layout
  • 20 MW AC capacity
  • Distributed inverter topology

Why the 2 × n configuration

  • Optimised land use
  • Improved airflow and thermal performance
  • Efficient maintenance access
  • String balancing
  • Reduced shading losses

Inverter system

  • 40 × 500 kW networked inverters
  • Real-time monitoring and remote diagnostics
  • Power-factor control
  • Voltage and frequency regulation
  • Redundancy, fault isolation and maintenance flexibility
ParameterSpecification
Installed capacity20 MWp
Modules40,000
MountingGround-mounted
Configuration2 × n layout
AC capacity20 MW
04

Grid interface and captive power delivery

Power is exported directly at 33kV to the industrial area via a dedicated feeder.

33kV switchyard

  • Step-up transformers
  • 33kV switchgear
  • Protection relays
  • Metering systems
  • Synchronisation equipment
  • SCADA integration

Power-delivery configuration

  • Embedded generation
  • Industrial-grade protection coordination
  • Revenue-grade metering at the point of delivery
  • Voltage and frequency compliance
  • Reduced transmission losses
  • Improved reliability and controlled pricing
05

Control and monitoring

Central Control Room

  • Energy Management System
  • SCADA servers
  • Communication infrastructure
  • Industrial-feeder monitoring
  • Protection and relay interfaces
  • Security monitoring

Energy Management System

  • Real-time performance analytics
  • Inverter-level monitoring
  • Industrial-demand tracking
  • Power-quality and alarm management
  • Historical data storage
  • Remote access
  • Dynamic response to industrial load fluctuations
06

Security and site infrastructure

The 100-hectare site is secured through systems integrated into the Central Control Room dashboard.

  • Full perimeter fencing
  • Vibration and motion detection
  • IP-based CCTV surveillance
  • Access-control gates
  • 24/7 monitored security operations
07

Engineering, construction and project management

Engineering

  • Feasibility and solar-resource studies
  • Electrical system design and industrial load profiling
  • Grid-interface protection and power-quality studies
  • Switchyard design
  • Civil and structural engineering

Construction

  • Site clearing and grading
  • Ground-mount structure and 40,000-module installation
  • 40-inverter deployment
  • DC/AC cable routing
  • Transformer and 33kV switchyard construction
  • Dedicated feeder and CCR construction
  • Security infrastructure deployment

Project management

  • Procurement and logistics
  • Contractor supervision
  • QA/QC and HSE compliance
  • Budget and schedule management
  • Commissioning and performance verification
08

Health, safety and environment

  • Comprehensive HSE plan
  • Zero major lost-time incidents
  • Environmental-impact mitigation
  • Controlled stormwater management
  • Waste-recycling protocols
09

Commissioning and performance

The plant achieved successful operational handover to the captive industrial customer operator.

Testing

  • String and insulation verification
  • Inverter functional testing
  • Transformer and switchgear testing
  • Protection-relay configuration
  • Load simulation
  • Synchronisation and industrial-load acceptance

Performance indicators

  • 20 MWp installed capacity
  • Availability above 99%
  • Stable 33kV supply
  • Reduced industrial downtime
  • Lower operational energy costs

Industrial impact

  • Reduced diesel consumption
  • Lower carbon footprint
  • Improved voltage stability
  • Reduced energy-cost volatility
  • Enhanced production reliability
10

Risk mitigation

RiskMitigation
Grid instabilityCaptive-supply configuration
Diesel fallback dependencyHigh-availability system design
Equipment failureDistributed inverter redundancy
Security threatsIntegrated surveillance
Load fluctuationEMS-based demand tracking

Sustainability impact

Engineering that moves the energy system forward.

  • Reduced diesel generator consumption
  • Lower carbon footprint and noise pollution
  • More predictable industrial energy pricing
  • A replicable model for industrial decarbonisation across West Africa

Explore the complete RESDAC project legacy.

Back to the timeline